To export a report to Excel for Hours Worked:
- Log into HammerTech (if you are not already logged in), then navigate using the left hand menu REPORTS > Hours Worked
- To run a company level report make sure you have selected 'Company Overview' from the project drop down in the top right corner of the screen.
- Select either Report Option 1 (Displayed by Employer Only, or Displayed by Employer & Individual)
- OR
- Select Report Option 2
- Enter in the Start Date and End Date
- Note: For an up to date report you may leave the End Date blank, or for a report of the entire project leave both the Start Date and End Date blank
- Select if you require the hours per Day/Week/Year or Total
- OR
- Select Report Option 3 (Effective Working Hours (total minus breaks), or Total Working Hours)
- Select the green Download Report icon
- The report will download in an Excel format